(**Schedule was created by Joe Rafferty and discussed with the group as the best choice**). (**Schedule was created by Joe Rafferty and discussed with the group as the best choice**).
------------------------------------------------------------------------------------------------------------------ ------------------------------------------------------------------------------------------------------------------
## **Determine the development goals for the Alpha and Beta Stage submissions:** ##
**Week 4 the Final Alpha is Due:**
* Have a playable demo.
* Code should be completed by this submission.
* Assets should be 50% completed with placeholders for the rest.
**Alpha:**
* Jump pad
* Pick-ups
* Virus Reproducing
* Capillaries
* Programming with HUD
* Level Design
* Health/Damage
**Week 5 the Final Beta is Due:**
* Code and Assets should be 100% completed by this submission.
**Beta:**
* Finished HUD assets
* Finished materials
* Finished icons for pickups
* Finished virus models with materials
**(The development goals were discussed and decided as a group).**
------------------------------------------------------------------------------------------------------------------